03 · Settlement
Reconciliation
Verify delivery against commitments to the 15-minute interval, attribute revenue to each asset, and reconcile against the ISO settlement statement. When an asset underperforms, the root cause is already attached.
SETTLEMENT · MAY 7 2026
RECONCILED
Interval meter data verified · 15-min granularity
DELIVERY SUMMARY
COMMITTED
8.4 MW
day-ahead position
DELIVERED
8.1 MW
verified · AMI metered
PERFORMANCE
96.4%
↓0.3 MW shortfall
8.1 MW delivered
0.3 MW shortfall
PER-ASSET ATTRIBUTION
Asset
Committed
Delivered
Performance
Revenue
Status
Meridian Warehouse
Battery · Site 1
3.4 MW
3.4 MW
100%
$1,870
SETTLED
Riverton Cold Store
HVAC · Site 2
1.1 MW
1.1 MW
100%
$490
SETTLED
NorthPark Mfg
Battery · Site 3
2.4 MW
2.1 MW
87.5%
$940
UNDERPERFORM
FleetCo Depot 4
EV Fleet · Site 4
0.8 MW
0.8 MW
100%
$310
SETTLED
Meadowbrook School
Battery · Site 5
0.7 MW
0.7 MW
100%
$210
SETTLED
⚠ UNDERPERFORMANCE · NORTHPARK MFG
Root cause:
SOC fell below 20% floor at 15:47 CT → emergency reserve triggered
Impact:
↓0.3 MW for 42 minutes · Performance penalty: −$124
Agent flagged risk at 14:52 CT → operator override declined dispatch reduction.
REVENUE WATERFALL
Gross settlement revenue$7,820
Performance penalty (ERCOT)−$124
Platform fee (18%)−$1,388
Customer net revenue
$0
From meter to payout
Every dollar, traced to an interval.
Settlement closes the loop: the same engine that bid and dispatched now proves what was delivered, attributes it per asset, and reconciles it against the ISO — penalty and all.
01 — VERIFY
Interval-metered delivery
AMI meter data is matched against the committed position at 15-minute resolution. Committed vs. delivered is reconciled before any revenue is recognized.
02 — ATTRIBUTE
Revenue per asset
Delivery is allocated proportionally with no rounding leakage, so each site carries its own performance and payout. Underperformers are flagged with a root cause.
03 — RECONCILE
Against the ISO statement
Gross revenue, ERCOT performance penalty, and platform fee resolve to a customer-net figure that ties out line-by-line to the settlement statement.